HIGHWAY 60 – DOWNTOWN RECONSTRUCTION Project Update (September 21, 2018)

Traffic

Please be advised that the Highway 60 (Raglan Street South/ Veterans Memorial Boulevard)/ Hall Avenue/ County Road 52 intersection will be closed to all traffic starting Monday, September 24th, 2018 until October 5th, 2018.

A Detour will be in effect for Highway 60 via Gillan Road, Hall Avenue and Plaunt Street.  A Detour for County Road 52 will be in effect via Airth Boulevard, Opeongo Road, Bonnechere Street South and Renfrew Avenue West.

 

Concrete Sidewalk    
 
Concrete sidewalks are completed on Bridge Street, Raglan Street North and Raglan Street South from Munroe Avenue to Renfrew Avenue West

Bonnechere Excavating Inc. (BEI)'s subcontractor will be returning October 2nd to complete sidewalks on Raglan Street South from Renfrew Avenue West to Hall Avenue.

 

Asphalt
 
Top lift of asphalt is scheduled for September 28th and 29th for Bridge Street, Raglan Street North and Raglan Street South from Munroe Avenue to Duke Street.

Base lift asphalt is tentative scheduled over the next two weeks weather depending, for Raglan Street South from Duke Street to Renfrew Avenue West. 

 

 

If you have any concerns related to the project or require special accessibility accommodations, please let us know by contacting the project manager noted below.  The Town of Renfrew would like to thank you with your patience and cooperation with this important construction project.

Lane Cleroux
Project Manager
Town of Renfrew
Phone: (613) 432-8166
Email: lcleroux@renfrew.ca